Precise trenching in Magnesium Limestone.
Note the reuse of cut material for pipe bedding and trench backfill.
(WS90 unit mounted on Komatsu PC-240)

Excavation
of footings for concrete foundation in magnesium limestone.
Note
the cutting
precision.
(WS60
unit mounted on Daewoo 220LC-V)
Precise trenching
in Magnesium Limestone.
(WS90 unit mounted on Komatsu
PC-240)
|
Specialist
UK ground works contractor Abrahams Brothers is making time and
cost savings with its first time use of Terex-Schaeff WS-60 and
WS-90 excavator mounted milling cutter attachments on a major retail
distribution centre project in South Elmsall, Yorkshire. The company
is installing water and sewerage services and foundations for the
vast new warehouse and is using the cutting units to neatly and
accurately excavate deep, vertically sided pipeline trenches, large
interceptor sewer tank excavations and form stanchion foundation
bases.
Abrahams Brothers has also found the Terex-Schaeff
cutting units to be considerably quieter and more versatile,
efficient and environmentally acceptable than traditional trenching
with noisy breakers. The company has established that the cutters
are able to considerably reduce the amount of material that would
have to be excavated in a battered trench with the traditional
excavator mounted breakers. The material excavated and pulverised
by the Terex-Schaeff cutters can also be recycled as trench backfill.
This considerable additional benefit contributes towards savings
on materials, transportation and lorry movements as the trenching
technique, with the Terex-Schaeff cutting units, eliminates the
need to cart away spoil and import new suitable backfill.
The company based in Dewsbury, West Yorkshire
and founded in the late 1980s by brothers John and Phil Abrahams,
specialises in ground works contracting and pipeline trenching.
Abrahams Brothers has mainly used a combination of excavators
and excavator mounted breakers to form trenches. However, the
company is always on the look out for new and alternative methods
to improve the efficiency of its operations. In the summer of
2003 a friend of Abrahams director John Abrahams suggested using
the Terex-Schaeff Cutting Units as an alternative trench excavating
technique.
Abrahams
Brothers needed an opportunity to try the Terex-Schaeff Cutting
Units and that came in March 2004 with
the award of a substantial 46 week ground works subcontract for
a new retail distribution warehouse. Abrahams Brothers, working
for main contractor Marshall Construction (West Yorkshire), had,
as part of its contract, to excavate about 800m of 1m to 5m deep
trenches up to 2m wide and interceptor tanks and manholes in
24.5 MPa compressive strength yellow magnesium limestone for
foul sewers and storm water drainage. In addition the specialist
contractor had to excavate around 280 footings for mass concrete
foundation bases to support the huge warehouse’s steel
stanchions.
“We initially hired a WS-90 Cutting Unit
from Terex-Schaeff to see if it could cope with the limestone
and deep trenches,” says John Abrahams. “We were
very pleased with it and it was a big success. It was able to
cut a very neat and accurate 5m deep, 1m wide trench and straight
down without any over break. We were also able to recycle and
reuse the excavated spoil, pulverised by the cutting unit, as
trench backfill. This was a major advantage as it contributed
towards savings on carting away and bringing in new backfill.
The trench would have been battered and much wider at the top
and the excavated spoil unsuitable as backfill if we had dug
and broken it out in the normal way with a breaker. The cutting
unit produced a much neater and accurate job with less damage
to surrounding areas. We were also able to neatly cut through
C35 concrete ground beams without damage to surroundings. It
reduces the amount of shoring needed, was also considerably quieter
than the breaker and with much less vibration has much less wear
and tear on the excavator.”
The
initial trial was so successful Abrahams Brothers bought the
WS-90. “We only had it about a week
and were so pleased with it we bought it and ordered a smaller
WS-60 at the same time and hired in a second WS-90 for the initial
phase of this job,” says John Abrahams. “We mounted
our WS-60 and WS-90 on our own 22t Daewoo 220LC-V excavators
and the hired WS-90 on a hired 24t Komatsu PC-240.” The
Terex-Schaeff Cutting Units are mounted on quick hitch attachments,
which are fitted on the end of the excavators’ dipper arms
in place of the host machines’ standard buckets. The Terex-Schaeff
Cutting Units, with their rotating tungsten carbide tipped cutter
drums, are driven from the excavators’ auxiliary hydraulic
circuit and pushed into the limestone. The rotating milling cutter
is simply moved back and forth along the trench line, gradually
increasing depth.
The WS-60 and WS-90 accurately form a straight
sided, flat-bottomed trench and after pulverising the material,
a second excavator follows on digging out the graded spoil to
complete a section of the trench excavation. The sections of
pipe are placed on a 150mm thick bedding layer of 10mm or 20mm
aggregate, which is also used as an initial 150mm thick covering,
prior to the pulverised spoil being placed back on top as backfill
and compacted.
Abrahams
Brothers is also using the Terex-Schaeff Cutting Units to excavate
the footings for the 5m x 5m x 3m deep
pipeline interceptor tanks, 20m3 manhole excavations and 1.2m
x 1.2m x 1m deep footings for the building’s stanchion
foundations. “Using the cutting units we form a clean slot
round the perimeter of these excavations to full depth and then
use a breaker to remove the remaining infill,” explains
John Abrahams. “We then trim the bottom of the holes with
the cutting units to form very neat and accurate flat bottomed
excavations. And because there is no over break or any damage
or shattering of the surrounding rock, which we would get if
we just used the breakers, we are able to make considerable savings
on concrete.”
Abrahams
Brothers is averaging about 30m3/day excavating the yellow
magnesium limestone with the smaller Terex-Schaeff
WS-60, while the larger WS-90 is averaging between 30m3 and 50m3/day. “This
is probably about the same speed had we used breakers, but we
are getting a much better finish and making savings on materials.
We bought 50 extra picks with the machines and on average only
change 1 to 2 picks a week. I’m very impressed with the
Terex-Schaeff Cutting Units and in the first two months on the
job they have so far contributed to knocking a week off our original
programme.”
|